On Center Home | MyOnCenter Portal | Start an On-Screen Takeoff Trial | Request a Quick Bid Demo | Contact Us | SALES: 1-866-627-6246
   
 
Learn more about Searching
Looking for help for one of ConstructConnect's Other products? Login


Tools
Table of Contents

Digital Production Control - 05.01 Tracking Production - Comparing Percent Complete to Labor Used - DPC

Views: 1288 Last Updated: 08/09/2024 10:18 am 0 Rating/ Voters
Be sure to rate this article 5 Stars if you find it helpful!

There are two things you must tell Digital Production Control for it to track your work crew's productivity:

  • How complete the job is - we call that "percenting" (indicating how "complete" each piece of takeoff is on each page of a project)
  • How much labor (hours) it took to get to that percent complete (the labor used) - tracked on the Timecard Tab (how much time it took your crew to do the work)

DPC takes the information you enter to calculate how close to "Budget" you are.

Remember, DPC uses color-coding to help you quickly identify how your project is progressing and which (if any) Labor Cost Codes are meeting production or falling behind:

Icon Color Code What it means...
in DPC blue status color-coding means work has not started Blue Percenting not started - no percenting has been set, no time has been entered against this LCC
in DPC green status color-coding means work has started and is on budget Green On Budget - the labor (time) you've used is meeting projections, based on the original estimate
in DPC orange status color-coding means work has started and is over budget by less than five percent Orange Over budget by less than 5% - the labor used to complete the percent complete is within 0% and 5% greater than expected
in DPC red status color-coding means work has started and is five percent or more over budget Red Over budget by over 5% - the labor used to complete the percent complete is within over 5% greater than expected

A little about Labor Cost Codes...

DPC uses the Labor Cost Codes from the Condition Details as priced in Quick Bid to track labor activity. Ensuring that you use well-defined Labor Cost Codes is important to accurately track labor. Labor Cost Codes can be tied to specific individuals or to specific work actions. This lets the Foreman and Project Manager see who is doing what, when they are doing it, and how efficiently they are doing the task. This information lets you dial in your crews. For instance, if you see that John is more efficient hanging drywall than he is building walls, you can assign him to hanging drywall when possible. The ability to "dial-in" your crew to maximize efficiency based on their strengths underscores the need to do accurate daily percenting.

Percenting tracks labor activity. It gives you real-time information, which allows you to recognize how close the job is to budget and completion. To percent a job in DPC select the Image Tab and go to the page that reflects where the work was performed. (This is why we recommend Collating pages to make percenting a job a lot easier, see Related articles for details.)

We will start with percenting in the next article. We cover timekeeping later in this section, see Related articles if you cannot wait.

click here to view the previous article Sending and Receiving Without Project Express The Basics of "Percenting" click here to view the next article



Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.

Something Wrong with this Article? Let us Know! The information in this site is protected by copyright by ConstructConnect. You may not reproduce, adapt, or publish any content from this site in whole or in part for any purpose, without the express written consent of ConstructConnect, Inc.
Copyright 2024 - All Rights Reserved.