To calculate projections (on the Bids and Budget Tabs), DPC requires that
Time be entered in the same place where work was performed (where objects were
percented). This means, if you used Bid Areas in your
Project, you must assign the Labor (Time) to the same Bid Area where the objects reside (and in the Base Bid or
Change Order where the
takeoff resides). If you apply Time to the wrong Area or to the wrong Base Bid/Change Order, the Budget Tab will not be able to calculate projected values correctly. The
Project Manager can set the option to "Ignore Bid Areas on Timecard" on the
Cover Sheet of the Bid before sending it out to the field, if you do want to group/break the Budget Tab by Bid Areas.