Quick Bid - 05.07 The Item Details Calculations Tab: Overview and Video - QB

Views: 985 Last Updated: 10/31/2024 09:25 am 0 Rating/ Voters
Be sure to rate this article 5 Stars if you find it helpful!

The Calculation tab defines how Quick Bid converts Condition Quantity to Item Quantity. This article (and those that follow) is a little long, but understanding "Calculations" is one of the most critical steps to getting your Item setup correct.

Example

If we consider pricing a very simple Wall. The (takeoff) quantity is probably calculated in LF (when you look at the a set of plans, you likely measure the wall from a birds-eye view). We will say the wall is 10' long and the Height of that wall is 8'.

Now, let us say you want to quantify the cost associated with applying paint to that wall (Material and the Labor required to 'install' that Material). You will probably start with a Condition Quantity in linear measurement (such as LF or meters) because that's how you'd measure the plans. But you wouldn't valuate Paint (Material) or Painting (Labor) by the LF, you'd first want to figure out the square footage (or square meters) of wall that needed Paint. In our example, 80SF. Also, that takeoff measurement does not take into account both sides of a wall or any waste factor.

The Calculation tab tells Quick Bid how to convert the Condition Quantity (usually from your takeoff program or quantity survey) into Item Quantity (on which QB can perform further calculations). You can calculate Item Quantity using any Condition Quantity (1, 2, or 3), the Height, the number of Layers, the on center measurement, even the number of vertical repeats, and how a Material is installed. You can even account for Waste, depending on how you setup your Item.


You specify the method of installation using calculation formulas embedded in the program and specify custom settings to calculate an Item's quantity. The Calculation tab offers many options that control the way Item quantities are computed.

There are five sections on the Calculation tab: Calculation Method, Condition Detail Default Entries, Formula Descriptions, Installation Method, and On Center Exception Factors. We'll start with Calculation Method in the next article and cover the rest in the articles that follow, just to make each article a little shorter and easier to digest.

Quick Bid Item Detail dialog box with Calculation tab active

Let us take a detailed look at each section of the Calculation tab, starting with Calculation Method.

click here to view the previous article Item Details - Chained ItemsThe Calculations tab: Calculation Method click here to view the next article

>


Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.

Something Wrong with this Article? Let us Know! The information in this site is protected by copyright by ConstructConnect. You may not reproduce, adapt, or publish any content from this site in whole or in part for any purpose, without the express written consent of ConstructConnect, Inc.