On Center Home | MyOnCenter Portal | Start an On-Screen Takeoff Trial | Request a Quick Bid Demo | Contact Us | SALES: 1-866-627-6246
   
 
Learn more about Searching
Looking for help for one of ConstructConnect's Other products? Login


Tools
Table of Contents

Digital Production Control - 04.06.03 Sending Updated Bid (with New Change Orders) to Field - DPC

Views: 680 Last Updated: 08/08/2024 09:21 am 0 Rating/ Voters
Be sure to rate this article 5 Stars if you find it helpful!

Once the Project Manager has finished adding Change Orders or changing labor/production, he or she needs to send the updated project file out to the Foreman (or Foremen).

Warning
One final warning - sending out a new DPC Package will overwrite the Foreman’s existing bid with the Project Manager’s changes. Any pending changes the Foreman (or foremen) did not send to the Project Manager will be lost - there is no way for the Foreman to send those changes to Project Manager once the Project Manager creates a new DPC Package. It is critical that all DPC Changes are sent to the Project Manager and incorporated into the Project Manager's database before the Project Manager sends a new *.dpm file to the field.
Be sure to coordinate between the Project Manager and each Foreman before sending/receiving new Bid Packages for existing projects.

See Related articles for more information on Sending project information.

Click Send > DPC Package > Via Project Express (or whatever method is used to transfer bid information) to send the updated project to the field (be sure to include the Est. Hours from the Budget Tab in the Subject line of the file you send to the field).

After the Project Manager returns an updated DPC Bid Package (dpm file) to the Foreman (or Foremen), the Foremen verifies they have imported the file correctly by comparing "Est. Hrs." on the Budget Tab to the Subject of the DPM File.

Review the Budget Tab and note the new budget estimated hours to include in the subject line of your project express file

Once the Foreman (Foremen) import the Bid Package, he or she can then resume percenting and entering time on the job as usual.

click here to view the previous article Returning Bid to DPC ModeSending and Receiving Without Project Express click here to view the next article



Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.

Something Wrong with this Article? Let us Know! The information in this site is protected by copyright by ConstructConnect. You may not reproduce, adapt, or publish any content from this site in whole or in part for any purpose, without the express written consent of ConstructConnect, Inc.
Copyright 2024 - All Rights Reserved.