Digital Production Control - 03.02.01 Project Manager - Archive Original Bid - DPC

Views: 726 Last Updated: 08/07/2024 08:22 am 0 Rating/ Voters
Be sure to rate this article 5 Stars if you find it helpful!

Archiving means storing a single copy of the original priced (sold) Bid for historical reference.

Warnings

While you were doing the takeoff and working up the estimate for a project, you may have duplicated a Bid many times to perform 'what if' scenarios. When you use Digital Production Control, you must use one copy of a Bid throughout the life of the job. You will make one archive copy of your sold Bid and that's it, no more duplicates.

Once a project is sent to the field, do not move the project to a different database or folder, do not copy and paste it, duplicate it, or rename it.

Changes Orders must be created in the DPC project, not the original "sold" project.

Duplicate the Original Bid

  • Open the job in On Screen Takeoff® (make sure Quick Bid is running and licensed, also)
  • Click the Cover Sheet button
  • Verify that the job is priced using Quick Bid Interactive
  • Verify that you used Typical Groups and Repeating Pages, not Typical Areas
  • Return to the Bids Tab in On-Screen Takeoff (always duplicate an Interactive bid from On-Screen Takeoff)
  • Duplicate the Bid by right-clicking on the bid and selecting "Duplicate",
  • When you are prompted to duplicate the Quick Bid job, click YES

When On-Screen Takeoff prompts you to duplicate the interactive Quick Bid bid, select Yes.

This creates an exact copy of both the On-Screen Takeoff and Quick Bid projects, linked in Interactive Mode. This duplicate copy is what is used in DPC - you will add the suffix "Archive" to the original...

Archive the Original Copy

Now, set the original Bid as your archive copy.

  • On the Bids Tab, select the Original Bid (not the duplicate copy)
  • Open the Cover Sheet
  • Change the Job Status to “Sold” (make sure "Sold" is set to "Lock Bid")
  • Add “ARCHIVE” (or something that clearly designates this as the original, "as-sold" project) to the Project Name

Note
This is your historic copy for reference only - do not use this archive copy for anything other than viewing what was originally sold. All DPC work and future changes are made to the DPC copy (the duplicate, what we will name the "BUDGET" copy...) going forward.

Change the Job Status to a locked one and add 'archive' to the bid name to differentiate it from the working bid

Budget Copy of Bid

On the Bids Tab, select the duplicate copy of the Bid

  • Open the Cover Sheet
  • Add “BUDGET” to the Project Name

Caution
The Project Name must be 25 characters or less when a Bid is in DPC Mode and must not contain special characters, see Related articles for restrictions.

  • Set the Job Status to “In Progress” or some Job Status that designates this project as being worked in the field/in the Project Manager's hands (make sure this status is not a 'locked' Job Status)

This is your working copy of the project for the duration of the job. Make no further copies/duplicates of this Bid.

In the duplicate bid, change the Job Status to 'in progress' and add 'budget' to the name.

Warning
This is the only duplicate copy of the project you should make. We stress this because it is very easy to accidentally use the wrong Bid later on and cause your DPC information to get out of synch with the field. Once out of sync, the only way to fix it is to start over.

click here to view the previous article Project Manager - Prepare Bid for DPC Project Manager - Collate and Organize Plans click here to view the next article



Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.

Something Wrong with this Article? Let us Know! The information in this site is protected by copyright by ConstructConnect. You may not reproduce, adapt, or publish any content from this site in whole or in part for any purpose, without the express written consent of ConstructConnect, Inc.
Copyright 2024 - All Rights Reserved.