Quick Bid - 10.02 How Labor Production is Calculated - QB

Views: 724 Last Updated: 10/21/2024 07:55 am 0 Rating/ Voters
Be sure to rate this article 5 Stars if you find it helpful!

Labor Production is the calculation of how much effort (work crew time) is required to complete/construct/install a specific amount of a Condition or Condition's component. For example, how many hours does it take a carpenter to frame 10 LF of 8' high wall or how many days does it take a crew of 3 to install 5,000 SF of roof? Production doesn't typically change with Quantity - it takes the same ratio of effort to material to build/install 10 LF of wall as it does 100 LF of wall.

There are three ways to adjust production (how much labor is required to build, install, finish, etc. a certain quantity of a particular Item, in a certain amount of time):

  • Adjust each line Item's production within a Condition's Item Detail Grid (detailed in this article)
  • Adjust Condition-level Labor Production which allows you to set production for all the Items included in a single Condition (see next article)
  • Adjust Bid-Level labor production on the Labor Tab (see the articles that follow)
Caution
Adjusting Labor Production in the Condition Item Detail Grid, explained in this article, does not affect other uses of this Item even in the same Condition. To adjust every use of a Labor Cost Code in the Same Condition, use the "Labor Adjust" button, described in the next article. To change Labor 'globally' in a Bid, adjust Production on the Labor Tab, described in Related articles.
Notes about Labor/Production
  • Labor may be viewed by unit price, production, piece count, time, or total money for a given Item
  • Production and time may be viewed either by the day or hour and by pieces or cut per duration
  • Production values may be modified by entering a percentage of the labor’s default rate

Controls to modify Item-level Labor/Production are accessed within the Item Detail Grid.

How Production Works

When you add an Item containing labor to a Condition, Production Rates are based on how you've setup the Master Item. You can click any labor value and change it directly within the Condition Item Detail Grid. Labor may be viewed in terms of cost, production, or time, but since all these values are inter-related, modifying one value changes the others for an Item.

All the calculations for Labor are based upon the Item Quantity ("Qty" in the Item Grid) for the Item being adjusted. If a Material or Labor Item defaults to one, two, or even four layers, Quick Bid still applies the labor to the Item quantity. The same principle applies to quantities that are entered directly. Calculated cost and man hours are the result of production or unit pricing applied to the Item Quantity.

To illustrate this:

Let us create a test Condition with a quantity of 100 LF and assign a height of 10’ 0”

Next, we drop-in Code "TT"(Top Track) - this is for demonstration purposes, of course, your database may not include this Item.

This Item defaults with 1 layer and displays a quantity of 100 LF (this particular Item has a very simple Calculation and doesn't include Waste, see Related articles for more information on setting up Item Calculation, including Waste Factor). The unit price or production is used to calculate time (Crew Hours) and total money and are all based on the Item quantity of 100 LF.

Quick Bid Condition Detail dialog box showcasing Labor Production

Next, we change the layers entry to "2" - the quantity becomes 200 LF, but the unit labor price (Lab. Cost) and production (% Base, Qty/Hr-Day) values remain the same - only total time (Crew Hours) and total labor money (Lab Total) are doubled...

Quick Bid Condition Detail dialog box showcasing Labor Production unchanged when Quantity changes

Note
Production (Qty/Hrs (or Days)) doesn't change when the Quantity is increased or decreased, only the Hours needed and associated Labor Cost change. Think of it this way - the same people are doing the same action - how much per hour/day doesn't change, it just takes longer to finish if there is more to do.

In the next few articles we show you how to adjust these Production rates.

click here to view the previous article Making Adjustments to Material, Labor, Equipment, Other, and Subs Expenses Adjusting Labor Production for a Single Item in a Condition click here to view the next article



Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.