On Center Home | MyOnCenter Portal | Start an On-Screen Takeoff Trial | Request a Quick Bid Demo | Contact Us | SALES: 1-866-627-6246
   
 
Learn more about Searching
Looking for help for one of ConstructConnect's Other products? Login


Tools
Table of Contents

Quick Bid - 03.10.01 Default Indirect Expenses for All Sections - QB

Views: 750 Last Updated: 11/04/2024 11:46 am 0 Rating/ Voters
Be sure to rate this article 5 Stars if you find it helpful!

Indirect Expenses can be setup for All Sections (below) or for Individual Sections (next article).

Click Tools > Default Markups/Indirect Expenses - the Default Markup (Master) dialog opens.

Quick Bid Default Markups dialog box

Double-click "Default markup for all sections" in the Default Markup (Master) dialog - the Default markup for all sections (Master) dialog opens.

Default Indirect Expenses dialog box for All Sections

Configure Indirect Expenses for Stock, Clean, Supervision, and Per Diem. Indirect Expenses are applied to Cost Codes - each Cost Code (Material and Labor) in the database must be configured/setup separately. See Related articles for additional information on how Indirect Expenses work. If you apply Indirect Expenses based on Labor, you must configure each Wage Type separately - settings for "Open", for example, are not applied to "Union".

Stock Tab

On the Stock tab, configure indirect expenses associated with stocking costs on all Materials (material quantity or cost) or Labor (payroll classes) in the database.

Choose a Calculation Method for Stock - to change the calculation method, click on the arrow in the Calculation Method field and click on the preferred calculation method:

  • Material Quantity - calculates how much it costs to stock the job based on the quantity of materials
  • Material Cost - calculates how much it costs to stock the job based on the cost of materials (material dollars)
  • Labor Hours - calculates how much it costs to stock the job based on the amount of labor hours used

Select a Result for the calculation method to be shown as either Labor Cost or Material Cost - to change how the result is shown, click the arrow in the Show result as field, and click on the preferred result.

Make any needed changes, additions or deletions to the Payroll Class, Percent, Installer, Wage Type or Cost Code - this can be done by typing in the cells or using the Lookup tool the lookup icon is a magnifying glass that opens the relevant master list.

Clean Tab

On the Clean tab, configure indirect expenses associated with clean up costs on all materials or payroll classes in the database. Determine Calculation Method and Show results as (same as the Stock tab).

Enter the Mat. (Material) Cost Code, Cost, and Cost Code.

Supervision Tab

On the Supervision tab, configure indirect expenses associated with supervision costs of a job. Click on the arrow in the Calculation Method field and click on the preferred calculation method.

  • Labor Cost - calculates how much it costs to supervise a job based on the Cost of labor (labor dollars)
  • Labor Hours - calculates how much it costs to supervise a job based on the number of hours of labor

Enter the Payroll Class, Wage Type, Percent, Supervisor, Wage Type and Cost Code.

Per Diem Tab

On the Per Diem tab, configure allowances for daily expenses for particular pay classes. Enter a number in the Per Hour or Per Day field for each Payroll Class. Entering a number in one of these fields calculates the other fields based on the number of hours set in a normal work day. Enter a Cost Code.

Calculation Methods

Method What it does/How it is used...
Material Quantity Allows you to configure Indirect Expenses calculations based on each Material Cost Code's cumulative quantity.
Material Cost Separates and displays the total estimated material cost (dollars) by material cost code. The dollars are multiplied by the percentage entered.
Labor Hours Calculates the cost to stock, clean or supervise a job based on the amount of labor hours. Each Payroll Class used must be configured separately.
Labor Cost (Supervision only) Calculates the cost to supervise a job based on the cost of labor (labor dollars).

At the Bid-Level, there is another Calculation Method for Supervision called "Duration". It is not possible to set defaults for the Duration method because it is based on the particular cost codes/labor used in a Bid. Please review Chapter 5 for information on configuring Bid-level Indirect Expenses.

Show Results As... What it does/How it is used...
Material Quantity Allocates the Indirect Expense costs to a specific Material Cost Code and calculates a Material Quantity for the end result.
Labor Cost Allocates the Indirect Expenses costs to specific Payroll Class and Labor Cost Code.

Note
Remember, if you setup Indirect Expenses based on Labor Cost or Labor Hours, you must configure the Defaults for each Payroll Class/Wage Type combination. Setting up "Carpenter - Union" would not apply IE to a Carpenter's Labor Costs if the Wage Type was "Open", as an example.

click here to view the previous article Setting up Default Indirect Expenses Default Indirect Expenses for Individual Sections click here to view the next article



Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.

Something Wrong with this Article? Let us Know! The information in this site is protected by copyright by ConstructConnect. You may not reproduce, adapt, or publish any content from this site in whole or in part for any purpose, without the express written consent of ConstructConnect, Inc.
Copyright 2024 - All Rights Reserved.