DPC - Quick Start Guide - 04.04 Collate Plans (drawings)
Views: 767 Last Updated: 10/20/2021 03:02 pm |
0 Rating/ Voters
|
|
Be sure to rate this article 5 Stars if you find it helpful! |
Open Cover Sheet of the "Budget" project
Click on a Page Title, then use the up and down arrows to sort the plan documents the way the job will be worked. For example, on a 2 floor project with floor plans and ceiling plans, you might organize it by floor 1, ceiling 1, floor 2, ceiling 2, etc. Try to keep the job organized in a way that will make working in the project easy.
Rename any Page Title to something more Foreman-friendly by clicking on the existing name and typing in a new name
Each page must have a unique Page Title
Each Alternate and Change Order must have a unique name
Flip Job to DPC Mode
|
|