Before you send a project out to the field, you need to review it to ensure it is set up properly for use in Digital Production Control. Open Cover Sheet of the "Budget" project
Click Areas
Review Areas and/or create as needed
Assign all of your takeoff to the appropriate Bid Area - see the On-Screen Takeoff User Guide for instructions

Confirm you have no takeoff in "Unassigned" (check the Takeoff Tab, Grouped by Area, Collapsed)

Next, make it easier for your Foreman or Foremen to navigate through the project plans.
|
|