|
|
Digital Production Control Quick Start Guide - 04.03 Setting and Verifying Bid Area Assignment - DPC
Views: 728 Last Updated: 07/30/2024 09:51 am |
0 Rating/ Voters
|
|
Be sure to rate this article 5 Stars if you find it helpful! |
Before you send a project out to the field, you need to review it to ensure it is set up properly for use in Digital Production Control. Open Cover Sheet of the "Budget" project Click Areas Review Areas and/or create as needed Assign all of your takeoff to the appropriate Bid Area - see the On-Screen Takeoff User Guide for instructions Confirm you have no takeoff in "Unassigned" (check the Takeoff Tab, Grouped by Area, Collapsed) Next, make it easier for your Foreman or Foremen to navigate through the project plans.
|
|