Digital Production Control Quick Start Guide - 05.06 Reviewing Progress - DPC
Views: 150 Last Updated: 07/30/2024 10:38 am |
0 Rating/ Voters
|
    |
Be sure to rate this article 5 Stars if you find it helpful! |
Click on the Budget Tab
Click the View as Hours radio selection - this makes the Budget Tab display more precise information about your project.
You now see the % Complete and Earned Hours for individual labor cost codes as well as for the entire job. 
Note the Earned Hours in the Total row - you will be adding this to the Subject line of your outgoing DPC Changes file
|
|