I Percented Everything to 100% in DPC Complete but Project does not show 100% Complete Overall

Views: 575 Last Updated: 02/22/2018 01:24 pm 0 Rating/ 1 Voters
Be sure to rate this article 5 Stars if you find it helpful!

So, you have set all your takeoff objects for all Cost Codes to 100%, but your Total % Complete is not 100%.

Why is my Project not 100% Complete?

The answer is "Indirect Expenses". Indirect Expenses are applied to Cost Codes automatically, but only get 'percented' as Time is entered on the Timecard Tab (labor is used). If you do not track labor expenses on the Timecard Tab, your project may never show Total 100% complete.

This only applies to Indirect Expenses that use Labor Hours as Calculation method and Labor Cost as the result or use Duration for Supervision. (Material costs are ignored by Digital Production Control.)