There are rules built into Digital Production Control that restrict what a user may send. These rules depend on which licenses are applied to your software (tko, dpc, dpm).

  • Only a user with a TKO (Takeoff license) is allowed to send an On-Screen Takeoff Bid Package (*.osp) from the product.
  • Only a user with a DPC Project Manager license is able to send a Complete DPC Package (*.dpm) for a DPC enabled project. The Project Manager must have Quick Bid installed and licensed and must have a tko and dpm licenses for On-Screen Takeoff/Digital Production Control.

On-Screen Takeoff/Digital Production Control Cover Sheet showing DPC Options

A Foreman cannot create a DPC Package file, they can send DPC Changes (*.dpc), Timecard Exports, and Budget Tab Exports back to the Project Manager only.



Product documentation (user guides) describes functionality in the latest version of each major release and may not match the functionality in the version you are using. Please check the Product Information and Downloads pages by clicking one of the product buttons above.

Something Wrong with this Article? Let us Know! The information in this site is protected by copyright by ConstructConnect. You may not reproduce, adapt, or publish any content from this site in whole or in part for any purpose, without the express written consent of ConstructConnect, Inc.
Copyright 2024 - All Rights Reserved.