Quick Bid - 10.05 Adjusting Labor Production at the Bid Level - QBAA-03991There are two ways of adjusting Labor (production) for an entire Bid (globally), both are done on the Labor Tab.
If you just want to change a single Condition or a single Item in a Condition, see the previous articles. Changing Labor Cost or Production One Row at a timeThe Labor Tab displays a row for every Labor Cost Code (LCC) used in a Bid. If you select "Show Production", each LCC is broken out by production (work/time). One row may represent the Labor associated with any number of Conditions (click the "View conditions in use" to see all Conditions in which a selected LCC is used). You can adjust the Production for any row (if you do not have "Show Production" checked, the production for the LCC is set the same where it is used, if you have "Show Production" checked, the production is updated only where it matches). Once you can see the four (yellow) production columns, you can make changes to the following fields to modify Production or Labor Cost:
The Prod. Updated (Production Updated) column displays the date the last update was made. You can also change Labor Cost/Production across the Bid by using the Labor Adjust box, similar to using the Labor Adjust in a Condition (Related article). Using Labor AdjustLabor production may be adjusted at the bid-level by using the Labor Adjust function on the Labor Tab. Open the Labor Adjust dialog box by clicking the Labor Adjust button in the upper right corner of the Labor Tab or right-clicking on a selected Cost Code (or codes) and clicking Labor Adjust. From this dialog, an estimator can modify production by entering days and/or hours or Cost. Updates to Crew Time updates the Cost and updates to Cost update the Est. Crew time. Warning Changing Labor Production on the Labor Tab updates this Cost Code for the entire Bid. Changes made on the Labor tab are immediate and permanent (no Undo function). To make changes in a 'What If' scenario, duplicate the Bid first, then make the changes in the copy without the risk of changing the original Bid. Note To revert production to default (as setup in the Master Item), click on the %Base on the Labor Tab and enter "100" - this restores the defaults from the Master Items. If you adjust Labor Production without the "Show Production" option checked, you are setting the LCC's production to the same rates, wherever it is used - the individual production rates cannot be restored, you'd have to adjust Item or Condition Labor within the Condition Detail. The Labor Adjust dialog box includes Labor from Conditions only - Equipment and Other Labor is not included. Make adjustments to the following in the Labor Adjust fields:
Click OK to make the changes to the Bid. Quantity, Qty/Hr (or Day), Cost, Total Cost, and Prod. Updated all update to reflect the changes. Prod. Updated always indicates the date of the last update made to Cost Codes. Note Adjustments cannot be made to Height, Description, Quantity, or UOM on the Labor Tab.
|